Public Schools of the Tarrytowns

Project Size: $2.9 Million
Cash Flow: $3.0 Million
Total Value: $5.9 Million
Completed: December 2012
Project Description:
Energy Performance Contract

.................................................
Annual Energy Savings: $235,237
Reduction in Energy Costs: 28.0%

.................................................

Project Description
When faced with needing to replace several expensive boilers during a weak economic period, administrators at Tarrytown UFSD decided to investigate whether these critical upgrades could be funded through Energy Performance Contracting (EPC). The result was a $2.7 million EPC that will replace 4 outdated boilers, as well as improve energy efficiency district-wide.

Project Highlights

  • lighting system upgrades
  • lighting controls - occupancy sensors
  • energy management system upgrades
  • steam hot water pipe and valve insulation
  • unit ventilator replacement
  • boiler/burner replacement
  • computer power management
  • infiltration reductions
  • GPS clocks
  • steam traps
  • kitchen hot water control valves