Patchogue UFSD


Project Size:
$2.6 million
Completion Status- est. September 2011
.................................................
Annual Energy Savings: $176,164
Reduction in Energy Costs: 25%

.................................................

When faced with needing to replace several expensive boilers during a weak economic period, administrators at Tarrytown UFSD decided to investigate whether these critical upgrades could be funded through Energy Performance Contracting (EPC).

The result was a $2.7 million EPC that will replace 4 outdated boilers, as well as improve energy efficiency district-wide. Other capital needs that will be addressed through the project include a partial roof replacement and selected window replacements, all of which will be funded with energy savings.

Project Highlights

  • lighting system upgrades
  • lighting controls - occupancy sensors
  • energy management system upgrades
  • steam pipe and valve insulation
  • unit ventilator replacement
  • boiler/burner replacement
  • computer power management
  • infiltration reductions
  • vending machine controls
  • domestic hot water heater
  • GPS clocks
  • steam traps
  • roof replacement