Project Size: $2.6 million
Completion Status- est. September 2011
.................................................
Annual
Energy Savings: $176,164
Reduction in Energy Costs: 25%
.................................................
When faced with needing to replace several expensive boilers during a weak economic period, administrators at Tarrytown UFSD decided to investigate whether these critical upgrades could be funded through Energy Performance Contracting (EPC).
The result was a $2.7 million EPC that will replace 4 outdated boilers, as well as improve energy efficiency district-wide. Other capital needs that will be addressed through the project include a partial roof replacement and selected window replacements, all of which will be funded with energy savings.
Project Highlights
- lighting system upgrades
- lighting controls - occupancy sensors
- energy management system upgrades
- steam pipe and valve insulation
- unit ventilator replacement
- boiler/burner replacement
- computer power management
- infiltration reductions
- vending machine controls
- domestic hot water heater
- GPS clocks
- steam traps
- roof replacement